Overview

Registration of lifts (elevators) and escalators with the inspection authority.

When Is This Required?

Parameter Condition Type
Has Lift equals true Required

Required Evidence

Application Input
Lift Inspection Certificate Must Sight Required

Validity & Renewal

Duration
12 months
Renewal Cycle
12 months
Renewal Lead Time
30 days before expiry
Lapses on inaction. This approval expires automatically if not renewed.

Legal Basis

Bangladesh Labour Act 2006 UNVERIFIED
Section Section 69(1) — Hoists and Lifts — Construction and Maintenance
Every hoist and lift in every establishment shall be (a) of good construction with sound material and adequate strength; (b) properly maintained; (c) thoroughly examined by a competent person at least once in every 6 (six) months, and a register shall be maintained containing such particulars, of every examination as may be prescribed by the rules.

Building360 interpretation — not legal advice: All lifts and hoists must be inspected by a competent person every 6 months with results recorded in a register. This is the legal basis for the Lift Registration and Lift Maintenance Log requirements.

Page 34
Bangladesh Labour Act 2006 UNVERIFIED
Section Section 69(3) — Hoists and Lifts — Safe Working Load
In every establishment, the capacity of safe working load shall be clearly written down on every hoist or lift and no load beyond such load shall be carried thereon.

Building360 interpretation — not legal advice: Lifts must have their safe working load capacity clearly displayed, and this load must not be exceeded.

Page 35
Bangladesh Labour Act 2006 UNVERIFIED
Section Section 69(6) — Hoists and Lifts — Additional Requirements
The following additional requirements shall be applied to hoists and lifts installed or reconstructed in an establishment after the commencement of this Act, namely: (a) where the cage is dependent on rope or chain, there shall be at least 2 (two) ropes or chains separately connected with the cage; (b) efficient devices shall be provided to support the cage together with its maximum load in the event of breakage of the ropes and chains; (c) proper automatic devices shall be provided to control the excessive speed of the cage.

Building360 interpretation — not legal advice: Post-2006 lift installations must have redundant suspension (minimum 2 ropes/chains), safety devices for rope failure, and overspeed governors.

Page 35

Approval Details

Type
Registration
Issuing Authority
DIFE
Lifecycle Phase
Operational
Typical Lead Time
~14 days
Validity
Subject to periodic inspection
Applies To
All multi-storey buildings with lifts

Requirements may vary by jurisdiction and project. Always confirm with the issuing authority.
Was this page helpful?
|

Stay informed

Building safety, compliance and operational readiness updates — direct to your inbox.

We respect your privacy. Unsubscribe at any time.